In Suh'dutsing Techs., LLC, the ASBCA held that the contractor could appeal a "deemed denial" of its certified claim 60 days after submission of the claim, notwithstanding the contracting officer's statement that it would be "at least another sixty days . . . before I am able to issue a decision." The Board held the CO's statement was "insufficiently definite" under the Contract Disputes Act, which requires a CO to, within 60 days of receiving a certified claim over $100,000, either issue a decision or "notify the contractor of the time within which a decision will be issued."


For more information, please contact the professional(s) listed below, or your regular Crowell & Moring contact.

J. Chris Haile
Partner – Washington, D.C.
Phone: +1.202.624.2898
Email: chaile@crowell.com

Brian Tully McLaughlin
Partner – Washington, D.C.
Phone: +1.202.624.2628
Email: bmclaughlin@crowell.com

Robert J. Sneckenberg
Partner – Washington, D.C.
Phone: +1.202.624.2874
Email: rsneckenberg@crowell.com

Crowell & Moring LLP is an international law firm with offices in the United States, Europe, MENA, and Asia that represents clients in litigation and arbitration, regulatory and policy, and transactional and corporate matters. The firm is internationally recognized for its representation of Fortune 500 companies in high-stakes litigation and government-facing matters, as well as its ongoing commitment to pro bono service and diversity, equity, and inclusion.

View Desktop Site | Mobile Sitemap |

Contact | Subscribe | Terms of Use | Privacy Statement | Alumni

© Crowell & Moring LLP 2022
Attorney advertising - prior results do not guarantee a similar outcome.